Old 01-08-2016, 03:17 AM
Margaret Pate Margaret Pate is offline Tasks with different durations to all finish on specific date Windows 10 Tasks with different durations to all finish on specific date Office 2013
Novice
 
Join Date: Dec 2015
Posts: 12
Margaret Pate is on a distinguished road
Default

Hi Nantia,

Don't worry about it, I post questions as well when I get stuck

One last question please, is there a "clever" way to calculate the optimal lag period? I would made the lag period the same as the duration of the preceding phase. For example, Server 1, Phase 1 has a duration of 3 days so the dependency for task 3 would be 7fs-3days.

Ideally in my project, all tasks should be sequential with no delay between them. So when we say that task 4 ('Pre-check') has dependency '7fs-10d' then this means that task 7 (phase 2) can start 10 days after task 4 has finished, correct? Correct - see above



Does it make sense to have a different lag period per server depending on the duration of phase 1? Or the lag period should not be related at all with the actual duration of the tasks of phase 1? Based on how I would approach it, it is related to the duration of phase 1.

Hope this helps,

Margaret
Reply With Quote
  #2  
Old 01-08-2016, 04:34 AM
Margaret Pate Margaret Pate is offline Tasks with different durations to all finish on specific date Windows 10 Tasks with different durations to all finish on specific date Office 2013
Novice
 
Join Date: Dec 2015
Posts: 12
Margaret Pate is on a distinguished road
Default

Another quick point - it might make it easier for you to view as you are starting up to have one of the standard formats - I think you have manually formatted the summary bars. As well as to have the weekends showing on the weekly view. See attachment 1

&You can then add flags and format the text bars so that they roll up to give the view that you want when you print it. See attachment 2 (look at it in print preview to see the key to the bars)

Regards,

Margaret
Attached Files
File Type: zip nantia_problem3 (2).zip (85.7 KB, 14 views)
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Tasks with different durations to all finish on specific date How to set a filter for tasks that will start & finish in two weeks? zislam14 Project 1 12-17-2015 03:58 PM
Tasks with different durations to all finish on specific date Finish to Start Tasks dates incorrect Rowey Project 5 05-01-2015 07:22 AM
Tasks with different durations to all finish on specific date % completion changes finish date? Puddlerunna Project 9 11-25-2014 06:16 AM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:04 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft