#1
|
|||
|
|||
|
Hope I haven't misunderstood what you are trying to do - I have attached what I meant with a before and after picture.
Regards, Margaret |
|
#2
|
|||
|
|||
|
I cant thank you enough Margaret, I do understand now!
One last question please, is there a "clever" way to calculate the optimal lag period? Ideally in my project, all tasks should be sequential with no delay between them. So when we say that task 4 ('Pre-check') has dependency '7fs-10d' then this means that task 7 (phase 2) can start 10 days after task 4 has finished, correct? Does it make sense to have a different lag period per server depending on the duration of phase 1? Or the lag period should not be related at all with the actual duration of the tasks of phase 1? Apologies for the multiple questions, I am newbie and I am struggling a lot! Thanks a lot! Nantia |
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
How to set a filter for tasks that will start & finish in two weeks?
|
zislam14 | Project | 1 | 12-17-2015 03:58 PM |
Finish to Start Tasks dates incorrect
|
Rowey | Project | 5 | 05-01-2015 07:22 AM |
% completion changes finish date?
|
Puddlerunna | Project | 9 | 11-25-2014 06:16 AM |
| flag to indicate finish date does not equal baseline finish date | TCB | Project | 3 | 08-06-2014 02:49 PM |
| remaining duration vs finish date | ketanco | Project | 3 | 02-17-2012 02:24 PM |