![]() |
|
#1
|
|||
|
|||
![]() Welcome ![]() Agreed lags are not the best way to do this (as I said before). For an alternative, you could relink phase 1 to phase 2 to phase 3, and then set the constraints on all phase 1 tasks to "as late as possible". This would mean that phase 2 to phase 3 would be a normal dependency (occurring one after the other), while the constraint would push phase 1 to its latest possible start, which would be controlled by the phase 2 date. Its probably easier to do than to explain, give it a try and see if it gives a better result ![]() |
#2
|
|||
|
|||
![]()
Many many thanks for all your help! I ll give it a try!
|
#3
|
|||
|
|||
![]()
Hello Guloluseus and happy new year!
I followed your recommendations and I ve placed all my 'phase 1' tasks with constraint "as late as possible" and I am getting slightly better results. In the attached mpp for example, if I change the start date of my phase 2 task in line 8 for example, then indeed I can see the whole summary task been shifted left or right. The other two summary tasks (line 12 and 22) also shift though and I do not understand why... I did not declare any dependency between them. In any case, I guess that with this approach this means that I will have to manually change the phase 2 start date of the hundreds tasks I have. Correct? This is gonna be difficult for me.. What I am trying to do is to "link" the phase 2 tasks of ALL my summary tasks with a milestone called 'PICK UP DATE' so I would only have to move the milestone and the respective linked tasks would be adjusted automatically. I would like all phase 2 tasks (i.e. lines 7, 17, 27) to start at the same time. This means that depending the duration of phase 1, some summary tasks should start sooner than others. I am still struggling with the dependency of this one, let me know if you can help! How could I link a milestone to my phase 2 tasks without messing with the sequential sequence of my tasks? Adding multiple dependencies in phase 2 task, makes things worse I think.. Regards Nantia |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Excel Gantt Chart Help | kpk250 | Excel | 0 | 03-08-2013 08:46 AM |
![]() |
sundance1 | Project | 1 | 01-29-2013 10:31 AM |
Bar in the Gantt chart with the duration | ms_user | Project | 3 | 01-11-2013 06:31 AM |
move to first date on gantt chart | etsoft | Project | 3 | 12-23-2011 08:32 AM |
Showing unscheduled tasks on Gantt chart | jaworski_m | Project | 0 | 11-20-2011 12:37 AM |