Leveling of resources ignores milestone links
Hi All,
I'm trying to create a program whereby individual tasks are linked and automatically scheduled according to a milestone. This is simple enough, the tricky part is that when I apply resources to project and then level the resources the links to the milestones are ignored... Any idea how to resolve?
A simple example is shown attached (before and after leveling). Note that my project has something like 170 drawings so the most automatic system will be first choice.
|