I'm guessing you are trying to get project to schedule from the milestone date forward? Have you tried scheduling from the finish date and using F to S links between Concrete and Reinforcing tasks? As a quick experiment, I set up your project tasks using a Project Finish date, created F to S relationships between the concrete drawing tasks and the reinforcement tasks.
|