JulieS JulieS is offline Leveling of resources ignores milestone links Windows 7 64bit Leveling of resources ignores milestone links Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I'm guessing you are trying to get project to schedule from the milestone date forward? Have you tried scheduling from the finish date and using F to S links between Concrete and Reinforcing tasks? As a quick experiment, I set up your project tasks using a Project Finish date, created F to S relationships between the concrete drawing tasks and the reinforcement tasks.
Attached Images
File Type: jpg peter 1.jpg (78.6 KB, 12 views)
File Type: jpg Peter.jpg (87.1 KB, 12 views)
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Leveling of resources ignores milestone links Leveling Resources Help! Mthomas88 Project 1 09-25-2015 08:25 AM
Leveling of resources ignores milestone links Certain Resources Not Leveling PDX-ADM-TRM01 Project 1 04-27-2015 03:45 PM
Leveling of resources ignores milestone links milestone with more than 0 day duration ketanco Project 3 06-16-2014 11:00 AM
Leveling of resources ignores milestone links Resources - only allow users to select from resources pool grazi Project 1 04-04-2014 11:12 AM
Milestone durations fraserm Project 4 01-13-2012 08:43 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:54 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft