#1
|
|||
|
|||
![]()
Hi All,
I hope this finds everyone well. Im trying to copy the resource usage data from MSP into Excel. Im sure this used to be a simple copy and paste exercise but clearly Microsoft have simplified it further into a long winded, complicated way. I understand that I can use a report for this but I really want it minute by minute so that I can do further calculations. Ideally it will have hours and minutes along the top and the resource or task down the left. Under the appropriate time it will just have a "1m" under it as per projects resource usage sheet. Does anyone know how to do this? Thanks Alex |
#2
|
|||
|
|||
![]()
I'm afraid your best choice is going to either be copy/paste or export through VBA. The visual reports do not go down to minute/hour level.
|
![]() |
|
![]() |
||||