Copy resource usage to excel
Hi All,
I hope this finds everyone well.
Im trying to copy the resource usage data from MSP into Excel.
Im sure this used to be a simple copy and paste exercise but clearly Microsoft have simplified it further into a long winded, complicated way.
I understand that I can use a report for this but I really want it minute by minute so that I can do further calculations.
Ideally it will have hours and minutes along the top and the resource or task down the left. Under the appropriate time it will just have a "1m" under it as per projects resource usage sheet.
Does anyone know how to do this?
Thanks
Alex
|