Duration & Work Hours Not Close
 
Join Date: Oct 2015
Posts: 1
fkistner is on a distinguished road
Unhappy Duration & Work Hours Not Close

Please help me -- I have a project Duration of 379 days and the Work is showing 27,797.65 hrs -- how could this be? I don't know what I am doing wrong? Here's a view of the insanity of these hours & days -- YIKES! How can a 21 day task equal all different amounts of work hours (they aren't even close to each other?) HELP ME PLEASE! THANKS!

Last edited by fkistner; 10-26-2015 at 01:17 PM. Reason: Graphic did not paste correctly as picture
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Duration & Work Hours Not Close Work vs. Duration Cameronk Project 1 05-14-2015 02:29 PM
Duration & Work Hours Not Close Resource not getting enough hours allocated to them, therefore extending duration joday48 Project 1 08-01-2014 08:54 AM
Duration & Work Hours Not Close Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Duration & Work Hours Not Close Work Week: hours vary each day rkc Outlook 1 08-31-2011 01:17 PM
Work not changing duration benoldays Project 0 02-14-2011 08:21 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 04:26 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft