Old 10-23-2015, 04:09 AM
Guloluseus Guloluseus is offline MS Project Date Range Issue Windows 7 64bit MS Project Date Range Issue Office 2010 32bit
Competent Performer
 
Join Date: Mar 2013
Posts: 168
Guloluseus is on a distinguished road
Default

The time filters in MSP tend to relate to task start and finish dates, and will not cut a task off- if a task starts/finishes within the specified time frame, then the task will be shown completely. As far as I know, there is no way to cut atask up in the way you want using these filters.
However, that doesn't mean it cant be done. As you superior is using Excel, I would suggest using the same output type. I use MSP 2010, but I assume that 2013 is fairly similar- sure someone can assist if the buttons are different.
Go into visual reports, under the Project tab, and choose either "Resource work availability" or "Resource work summary"- one of these will give a result that is most likely the one you want, but will need to try both to see which is best for you. select the chart and choose the level of usage- I generally go weeks, as days can take a while, but again depends what you want- then click view. In the excel sheet that comes up, you can change date ranges to actual dates (non task dependent) and show whichever work attribute is suited (generally "work" will give actual or predicted hours). Filter by date range and resource to the level you want, and you have a nice graph that should appeal to the excel minded person who wants to keep it simple.

If this doesnt give what you want or you need more help with anything, let us know- sure others will have other solutions too
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Formula for sumifs with less than a date range lynchbro Excel 6 04-15-2015 01:18 PM
MS Project Date Range Issue Count how many have completed each Training Course within a Date Range dmcmillion Excel 3 10-20-2014 09:59 AM
MS Project Date Range Issue Restrict Date Range Calculations akatz85 Excel 4 03-27-2014 08:46 PM
MS Project Date Range Issue Date Range Prompt MikeWooZ Excel 6 12-04-2011 02:10 PM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 05:06 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft