JulieS JulieS is offline Start date of successor task does not change Windows 7 64bit Start date of successor task does not change Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What are the links between your tasks Finish to Start? Start to Start? If everything is linked Finish to Start AND the tasks are autoscheduled AND you have split in progress selected even if task 20 has an actual start date (before its predecessor finished) and remaining part of the task should still be honoring the F to S link.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project 2013 - Change GANTT Bar Colour By Main Task Date CaelanT Project 1 02-09-2015 12:50 PM
How to make a task adjust its end date depending on another task? (Newbie) ravl13 Project 3 07-27-2014 06:10 PM
Start date of successor task does not change seeing successor information for a task ketanco Project 1 06-02-2012 09:35 AM
Task with Start date but no Due date? bplat Outlook 0 01-12-2012 08:10 AM
Start date of successor task does not change Task Start and End Dates OTPM Project 2 12-04-2011 09:14 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:26 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft