![]() |
|
#2
|
|||
|
|||
|
No it will not change because the successor task has an Actual Start date and Actual Start dates trump scheduled start dates. If a successor has been started, why would you want to change the start date later on?
However, if you have allowed splits in in-progress tasks (Options, Schedule) the successor task's remaining work should be scheduled based upon the original link relationship. |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Project 2013 - Change GANTT Bar Colour By Main Task Date | CaelanT | Project | 1 | 02-09-2015 12:50 PM |
| How to make a task adjust its end date depending on another task? (Newbie) | ravl13 | Project | 3 | 07-27-2014 06:10 PM |
seeing successor information for a task
|
ketanco | Project | 1 | 06-02-2012 09:35 AM |
| Task with Start date but no Due date? | bplat | Outlook | 0 | 01-12-2012 08:10 AM |
Task Start and End Dates
|
OTPM | Project | 2 | 12-04-2011 09:14 AM |