![]() |
|
#2
|
|||
|
|||
|
Assuming you have shifts of resources, yes. Create resources in the resource sheet and then create a day shift and night shift calendar. Assign the calendars to the resource(s). You can also create a 'team' by increasing the max units. For example, if you have 5 people on the day shift, set the max units to 500%. You can then assign the 500% (5 people) to the task and see the correct work calculated.
|
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| 12 hour work days (shifts) | John Franklin | Project | 22 | 11-12-2013 03:19 PM |
| 12 shifts/7 days | John Franklin | Project | 1 | 11-11-2013 09:11 AM |
Calendars, 12 hr shifts, 24 hrs/ 7 days
|
John Franklin | Project | 3 | 10-30-2013 08:16 AM |
| calendar for rotating shifts | dude1 | Excel | 0 | 05-29-2011 01:58 PM |
| IF statements that shifts to right. | kent | Excel | 0 | 01-19-2006 02:23 PM |