Old 08-09-2015, 08:35 AM
JulieS JulieS is offline Bottom Up Estimating Windows 7 64bit Bottom Up Estimating Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Sorry - project can calculate work based upon Duration and assignment units - but not based upon cost. I'd set up the information you know (estimated work), cost per resources and let project calculate the projected costs.

You can fix the duration - enter the work and project will calculate the assignment units necessary to get X amount of work done in Y time.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Paginate table so cell headings appear top of page instead bottom page when no room bottom page mtcn Word Tables 5 12-11-2014 12:49 PM
Bottom Up Estimating Top & bottom margins cryptogram Word 2 08-21-2014 02:00 PM
Bottom Up Estimating Underline at bottom of page won't go away yachts66 Word 3 08-13-2014 07:28 AM
Estimating total usage incidence from samples Saga123 Excel 0 01-18-2013 01:18 PM
How to get lines all the way to bottom PhyllisAStewart Word 2 08-18-2012 02:52 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:15 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft