Hi



So I went back into my original file and re-set a baseline. I again updated the tasks to show the actual start and finish times my Site Manager gave me, while checking on future tasks which were 'Late'.

As I began to update the tasks as completed I noticed that tasks further down the schedule which were 'Late' began to show as 'On Schedule' or 'Future'. These shouldn't be because my project is running behind schedule and several of these now 'On Schedule' or 'Future' tasks should have been completed 3 days before the current Status Date.

Is this change happening because Project is automatically rescheduling tasks due to the project drifting from the original baseline schedule which I had set?

I would like to show tasks which are 'Late' against the baseline.

Thanks
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Project Status and Late Tasks - Incorrect Finish to Start Tasks dates incorrect Rowey Project 5 05-01-2015 07:22 AM
RAG Status on Project 2013 deepsk Project 3 04-23-2015 07:26 AM
How to modify send status report in tasks office 2010 jonyorker Outlook 0 03-03-2015 07:31 AM
Filter - Late Tasks EC37 Project 3 06-12-2014 08:57 AM
Incorrect Task Status OTPM Project 0 03-24-2014 04:32 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 09:01 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft