#1
|
|||
|
|||
![]() Hi All I have an interesting question on a tasks status. Basically one of our PMs is trying to update a task which is showing as late but in real terms it is not late. Here is the scenario: Task duration is 2 days. Start date is 6 March and finish date is 1 Apr. Actual work so far is 8hrs on 6 March and 7.83hrs on 7 March. Future work is 0.17hrs on 1 Apr. However the Status is showing as Late and I am a little puzzled as to why. Can anyone help? Thanks Tony Edit: Sorted. The PM was using %Complete to record Actual % Completion rather than Physical % Completion. Last edited by OTPM; 03-24-2014 at 05:56 AM. Reason: Resolved |
|
![]() |
||||