New User Here. Can anyone tell me if a single task can have a different calendar than the rest of the tasks?
Example: Notice to Proceed: 15 calendar days after award of contract. (7 days a week) Mobilization: 2 work days. M-F E&S: 10 work days etc M-F End of Project: 90 calendar days after Notice to Proceed. (7 days a week) I have to make a preliminary schedule with no fixed dates. Any help would be appreciated. |
#2
|
|||
|
|||
![]()
Yes, it can. However, it doesn't sound like you need a different calendar - just to measure the lags in "edays".
For example: Contract award is the predecessor to Notice to Proceed. The link is Finish to Start with a 15 edays lag. Edays lag will count calendar (not working) days. |
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
Export calendar events from multiple calendars with specific title | rasmus | Outlook | 0 | 02-06-2015 01:58 AM |
Syncing Calendar to Iphone created 2 Mod calendars | MidInternet | Outlook | 0 | 05-21-2012 12:59 PM |
![]() |
GreenEcoChick | Outlook | 1 | 06-16-2011 02:45 PM |
Change Calendar to 4 day work week | J C M | Outlook | 1 | 04-28-2011 02:20 PM |
Can't get to my calendar since it's not the default user | TraderViccc | Outlook | 1 | 08-06-2010 05:08 AM |