Yes, it can. However, it doesn't sound like you need a different calendar - just to measure the lags in "edays".
For example:
Contract award is the predecessor to Notice to Proceed. The link is Finish to Start with a 15 edays lag.
Edays lag will count calendar (not working) days.
|