#2
|
|||
|
|||
|
Yes, it can. However, it doesn't sound like you need a different calendar - just to measure the lags in "edays".
For example: Contract award is the predecessor to Notice to Proceed. The link is Finish to Start with a 15 edays lag. Edays lag will count calendar (not working) days. |
|
|