![]() |
#2
|
|||
|
|||
![]()
Sorry, I must clarify the question.
The task is common to two resources: resource A with 100% unit, resource B with 0% unit, the task's duration is 5 days for example. In the "Team Planner" view I can see the task for resource A, but I cannot see the same thing for resource B: how can I do this? |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
AmmeLane | Project | 1 | 06-06-2014 06:42 AM |
![]() |
steve086 | Project | 3 | 01-10-2014 03:11 PM |
Refining Team Planner View in MS Project 2010 | CarolinaGamecock | Project | 1 | 11-27-2013 12:18 PM |
![]() |
Tray | Project | 9 | 07-07-2013 03:44 PM |
![]() |
david_23 | Project | 9 | 04-19-2012 08:33 AM |