  #1  
Old 04-24-2015, 06:03 AM
Rowey Rowey is offline Finish to Start Tasks dates incorrect Windows 7 64bit Finish to Start Tasks dates incorrect Office 2010 64bit
Novice
Finish to Start Tasks dates incorrect
 
Join Date: Apr 2015
Posts: 3
Rowey is on a distinguished road
Default Finish to Start Tasks dates incorrect

Hi all, I have a Project where when I schedule 80% of my tasks with a FS relationship I get the following scenario:

Task 1 - 12/01/2015 - 13/01/2015
Task 2 - 14/01/2015 - 15/01/2015

This is how I would expect task dates to appear however for 20% of my Project I get the following scenario:

Task 1 - 12/01/2015 - 13/01/2015


Task 2 - 13/01/2015 - 14/01/2015

The 2nd Task starts on the same day as the last day of the first task

Can anybody think why this may be occurring?

Thanks in advance
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Finish to Start Tasks dates incorrect Milestones with different start and finish dates ketanco Project 2 09-17-2014 05:21 PM
Finish to Start Tasks dates incorrect Changing Actual Finish dates changes original Finish dates SomewhereinTX Project 3 12-20-2013 10:25 AM
start and finish dates exceeding duration joday48 Project 0 06-27-2012 04:55 AM
Finish to Start Tasks dates incorrect duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
Finish to Start Tasks dates incorrect displaying start and finish times as absolute numbers instead of dates benson.wallace Project 2 12-05-2010 07:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:11 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft