Default Finish to Start Tasks dates incorrect

Hi all, I have a Project where when I schedule 80% of my tasks with a FS relationship I get the following scenario:

Task 1 - 12/01/2015 - 13/01/2015
Task 2 - 14/01/2015 - 15/01/2015

This is how I would expect task dates to appear however for 20% of my Project I get the following scenario:

Task 1 - 12/01/2015 - 13/01/2015
Task 2 - 13/01/2015 - 14/01/2015

The 2nd Task starts on the same day as the last day of the first task

Can anybody think why this may be occurring?

Thanks in advance