Hi Jules,
Please see example below Task Start End Baseline Start Baseline Finish Testing 23/04 23/04 22/04 22/04 with the above I need the status indicator to show a Red RAG status but when you change the baseline dates to 23/04 it will go back to green indicating the task is no longer overdue does that help? |
|
![]() |
||||