![]() |
#1
|
|||
|
|||
![]()
Hi there,
I'm new to the forum and would regard myself as a MS Project of novice/maybe intermediate level. I'm currently using MS Project 2013. I'm having problems with using, creating and managing a resource pool linked to a project. I have developed a project plan which I have assigned resource too. Within the resource pool itself I have added my work resources (employees) and recorded their holidays in the Change Working Time window under 'Exceptions'. I have then added two tasks which require 5 and 6 employees respectively to complete the tasks at a clients site. I have then assigned these two groups of employees to each of the tasks and set the tasks to Fixed Duration. In basic terms I'm looking for a simple way to manage employees availability for work on a project. I was hoping/expecting MS Project to identify a problem with the resource when I allocate employees to tasks, possibly as a resource overallocation. However, no such luck and when I look at Team Planner view the vacations don't appear. Can MS Project be used in this way? Thanks in advance |
#2
|
|||
|
|||
![]() Quote:
However, if the task is fixed duration, the story is slightly different. If the resource has non-working time s/he will simply have less work scheduled - assuming you changed the working time BEFORE assigning them to a Fixed Duration task. For example: a task starting on April 13, 10 days duration. Fixed Duration. Task is scheduled to finish on April 24. I have four resources: Mary, Mike, Pete, Sue. Pete is on vacation from April 21-24. I assign all four resources to the task. Mary, Mike, and Sue are all scheduled for 80 hours of work each. Pete is scheduled for 48 hours - the six working days in his schedule that fall between the 13 and 24. Take a look at the Task Usage view to really see when each resource is working. I do see Pete's shortened work schedule in the Team Planner view, but by default the task bars extend through nonworking time. Try changing the Nonworking time display to a darker color and you should be able to see the non-working time for each resource. |
#3
|
|||
|
|||
![]()
Hi Julie, thanks for replying. Very helpful indeed.
I was wondering if I could pester you about another issue I have just experienced. I have a project plan in place and have regularly been using the Filter to display 'Incomplete Tasks'. However, strangely when I tried to use this filter option today I found many of the standard in-built filters had disappeared, including the filter for Incomplete Tasks. Any idea why this has happened and how I can resolve it? Thanks |
#4
|
|||
|
|||
![]()
I see you've posted this as another question. I've answered you there.
|
![]() |
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
More assignments to email | NNat111 | Outlook | 1 | 06-19-2014 07:14 AM |
Hotkey assignments in template for others | ChrisBrewster | Word VBA | 1 | 02-14-2014 04:51 PM |
How to show Vacations at the Bottom of Work Schedule in Office Project 2007? | Rahmat_uk20 | Project | 3 | 06-08-2012 01:53 PM |
![]() |
mikelanne | Project | 1 | 12-04-2011 11:51 AM |
Change to Normal.dot not reflected | lanchka | Word | 0 | 07-11-2009 01:17 PM |