#1
|
|||
|
|||
![]()
If you have allowed tasks to be split during leveling, Project will take a task and "chunk" it into smaller pieces. As long as the task is not Fixed Duration, the splits (where the task is not working) will not count in the duration.
|
#2
|
|||
|
|||
![]() Quote:
thank you. how does one allow or not allow a task to be split? |
![]() |
|
![]() |
||||