Default

If you have allowed tasks to be split during leveling, Project will take a task and "chunk" it into smaller pieces. As long as the task is not Fixed Duration, the splits (where the task is not working) will not count in the duration.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Question about leveling a project..... VB Project in PowerPoint 2007/10 (Game Concept Question) theculpeppers PowerPoint 4 11-07-2014 06:08 AM
Question about leveling a project..... How do you shut off/ignore resource leveling pmgreen Project 1 08-22-2014 06:54 AM
Question about leveling a project..... MS Project 2010 - 'Who Does What When' report question jrdunn78hawk Project 5 06-24-2014 07:00 AM
Question about leveling a project..... resource leveling in ms project ketanco Project 1 12-24-2011 12:58 PM
Question about leveling a project..... New to project - Predecessor Question geissap Project 1 01-20-2011 10:00 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 07:34 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft