PDX-ADM-TRM01 PDX-ADM-TRM01 is offline Allocating resources based on efficiency Windows 7 64bit Allocating resources based on efficiency Office 2013
Novice
Allocating resources based on efficiency
 
Join Date: Dec 2014
Posts: 3
PDX-ADM-TRM01 is on a distinguished road
Default Allocating resources based on efficiency

Hi all - this is my first post here, so please let me know if I'm doing anything incorrectly.

I have resources assigned to a task, but I was wondering if Project had the capacity to go one step further, specifically using resources from a "pool" and assigning them.



Let's say I have Resource A, Resource B, Task C, and Task D. Both A and B can work on Task C and D, but A is much better at both of them. If there isn't enough time for Resource A to complete both tasks C and D, I'd like Project to assign Resource B to one of the task to make sure both get done on time.

Is this possible? Do I need to add additional clarification?
Reply With Quote
  #2  
Old 12-13-2014, 02:39 PM
JulieS JulieS is offline Allocating resources based on efficiency Windows 7 64bit Allocating resources based on efficiency Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Hi and welcome to the forum.

Sorry to say, Project will not automatically do what you seek. It has no method of "knowing" that Resource A is more skilled than Resource B. Project will not automatically assign a resource to any task - that is up to the user to select the best resource as well as watch any deadlines.

I hope this helps and feel free to post back with further questions.
Reply With Quote
Reply

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
Allocating resources based on efficiency Best practice when allocating a period of time to a number of tasks jgregs Project 3 07-25-2014 10:43 AM
Allocating resources based on efficiency Allocating multiple resources to a task and splitting the hours pptdgc Project 1 07-22-2014 03:45 AM
Allocating resources based on efficiency Resources - only allow users to select from resources pool grazi Project 1 04-04-2014 11:12 AM
Better way to views resources? ctobola Outlook 1 03-20-2014 08:01 AM
Allocating resources based on efficiency Total Resources 602chrislys Project 1 10-04-2010 09:04 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 03:57 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft