Hi and welcome to the forum.
Sorry to say, Project will not automatically do what you seek. It has no method of "knowing" that Resource A is more skilled than Resource B. Project will not automatically assign a resource to any task - that is up to the user to select the best resource as well as watch any deadlines. I hope this helps and feel free to post back with further questions. |
|
![]() |
||||