  #1  
Old 11-18-2014, 04:10 AM
Puddlerunna Puddlerunna is offline % completion changes finish date? Windows Vista % completion changes finish date? Office 2010 32bit
Novice
% completion changes finish date?
 
Join Date: Sep 2014
Posts: 17
Puddlerunna is on a distinguished road
Default % completion changes finish date?


Hi again,

found a new amazing feature in Project that I don't get

I have set up a project plan and all plan dates incl. dependencies look fine. Now as soon as I enter any value in the % completion field of the first task, the plan finish date changes to a later date. Why?

For the following tasks, no such issue occurs. It's just that single task.
Also, this will happen on any value, i.e. even if I set 90% with which we'd be ahead of plan, it'll change.
Reply With Quote
 

Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
what to put in to schedule for dealing with overall finish date ketanco Project 7 10-30-2014 02:25 PM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
Assigning finish date to work with %complete Guloluseus Project 3 12-12-2013 10:16 AM
% completion changes finish date? how to calculate backwards from a set finish date ketanco Project 1 02-07-2013 06:50 AM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:21 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft