When I open the file and press F9, I get immediate error messages about task 97.

I can reproduce your exact issue when mixing ALAP summary tasks with ASAP subtasks. The tasks split and the remainder of the task aligns with the ALAP constraints.
Reply With Quote
  #2  
Old 11-24-2014, 11:47 PM
Puddlerunna Puddlerunna is offline % completion changes finish date? Windows Vista % completion changes finish date? Office 2010 32bit
Novice
% completion changes finish date?
 
Join Date: Sep 2014
Posts: 17
Puddlerunna is on a distinguished road
Default

Ok, I think I need to reconsider the complete scheduling as this keeps causing the weirdest issues.

Thanks for your help
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
what to put in to schedule for dealing with overall finish date ketanco Project 7 10-30-2014 02:25 PM
flag to indicate finish date does not equal baseline finish date TCB Project 3 08-06-2014 02:49 PM
Assigning finish date to work with %complete Guloluseus Project 3 12-12-2013 10:16 AM
% completion changes finish date? how to calculate backwards from a set finish date ketanco Project 1 02-07-2013 06:50 AM
remaining duration vs finish date ketanco Project 3 02-17-2012 02:24 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:34 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft