Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #2  
Old 11-17-2014, 05:42 AM
JulieS JulieS is offline budget reports in MS Project Professional 2013 Windows 7 64bit budget reports in MS Project Professional 2013 Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

On the Report ribbon you can create a custom report. I'd use a table to show the data. All of the fields you need are available - the only tricky one is the Fixed Cost Accrual is under "other" in the field list.
Reply With Quote
 

Tags
budget report, ms project 2013



Similar Threads
Thread Thread Starter Forum Replies Last Post
Remove resource name from Gannt Bar in Project Professional 2013? nick@johansens.eu Project 1 10-16-2014 05:58 AM
budget reports in MS Project Professional 2013 MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table billcary Project 3 09-22-2014 07:10 AM
Cash flow reports in MS Project 2013 sansrini18 Project 3 09-09-2013 06:06 AM
running reports out of ms project nmanus Office 0 09-09-2009 12:47 PM
Connectivity issue of Project Professional with Project Server kashif Project 0 03-27-2009 06:37 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 08:59 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft