Microsoft Office Forums

Go Back   Microsoft Office Forums > >

 
 
Thread Tools Display Modes
Prev Previous Post   Next Post Next
  #1  
Old 07-21-2014, 11:41 AM
pptdgc pptdgc is offline Allocating multiple resources to a task and splitting the hours Windows 7 32bit Allocating multiple resources to a task and splitting the hours Office 2013
Novice
Allocating multiple resources to a task and splitting the hours
 
Join Date: Jul 2014
Posts: 1
pptdgc is on a distinguished road
Default Allocating multiple resources to a task and splitting the hours

Hi there,



I have a number of tasks in MS Project where I need to assign multiple resources but I don't know how to configure this so the cost comes out correctly.

For example I have a task where I know we have 20 days to complete it. I also know the task will be 280 hours of work in total. I have therefore set this to a 'fixed duration' task type at 20 days duration and 280 of work. With the resource availability i know one resource will spend 144 hours on this and the other 136 hours during this 20 day period.

When I assign two resources it automatically sets the units per person as a percentage.

Is there a way I can just manually enter the number of hours each person will do? I need to do this so my costs add up.

Perhaps I have configured this wrong?

Thanks for the help
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Allocating multiple resources to a task and splitting the hours Mid-Task resource scheduled 0 hours increasing task duration needlessly DarlaWeber Project 1 01-31-2014 02:30 PM
Allocating multiple resources to a task and splitting the hours How to set task to be done by 4 resources each one after another? lukusm Project 1 01-16-2012 07:21 AM
Allocating multiple resources to a task and splitting the hours several task must be completed out of hours, not split proj Project 1 01-13-2012 08:38 AM
Splitting multiple pages using macro F5JASON Excel Programming 0 07-27-2011 08:22 AM
Splitting Excel cell into multiple ruben23 Excel 1 07-23-2009 03:49 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:04 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft