patrickd123 patrickd123 is offline Unexpected behavior of actual finish Windows XP Unexpected behavior of actual finish Office 2003
Novice
Unexpected behavior of actual finish
 
Join Date: Dec 2011
Posts: 21
patrickd123 is on a distinguished road
Default

Related question: A task of 4 days starting on Monday. On wednesday morning, I click the 25 percentage button. Since it means that there is 3 days remaining, it should stretch the project to the Friday inclusive. But it does not.

Curiously enough, if instead, I go to the resource usage, I enter 8 hours actual on Monday and 0 hours actual on Tuesday, THEN, it detects that I am missing a day and it stretches the task to the Friday!!!!!

In theory, both situations are identical but MS project does not behave the same for both!

Any idea why?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Unexpected behavior of actual finish Changing Actual Finish dates changes original Finish dates SomewhereinTX Project 3 12-20-2013 10:25 AM
Unexpected behavior of actual finish duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM
Document Format: unexpected changes JMB^3 Word 1 08-19-2009 01:12 PM
Unexpected Server Response GreenAccord Project 0 01-31-2006 12:52 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 01:09 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft