Related question: A task of 4 days starting on Monday. On wednesday morning, I click the 25 percentage button. Since it means that there is 3 days remaining, it should stretch the project to the Friday inclusive. But it does not.
Curiously enough, if instead, I go to the resource usage, I enter 8 hours actual on Monday and 0 hours actual on Tuesday, THEN, it detects that I am missing a day and it stretches the task to the Friday!!!!! In theory, both situations are identical but MS project does not behave the same for both! Any idea why? |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
Changing Actual Finish dates changes original Finish dates
|
SomewhereinTX | Project | 3 | 12-20-2013 10:25 AM |
duration vs actual start and finish dates
|
ketanco | Project | 1 | 12-14-2011 09:06 AM |
| MS Project able to import actual start and or actual finish date from Excel? | mhacker | Project | 0 | 04-26-2010 11:29 AM |
| Document Format: unexpected changes | JMB^3 | Word | 1 | 08-19-2009 01:12 PM |
| Unexpected Server Response | GreenAccord | Project | 0 | 01-31-2006 12:52 PM |