#1
|
|||
|
|||
![]()
Hi,
I did a simple test to try to isolate the behavior but in vain! Let's say a simple task of 40 hours starting on Monday the 10th supposed to finish on Friday the 14th. Then on the Wednesday I click 100% completed. In my mind, I the actual finish date should switch from N/A to 12th but instead it shows the 14th, which is the original finish date. Makes no sense to me! Any idea? Last edited by patrickd123; 07-15-2014 at 08:53 AM. |