Hi,



I did a simple test to try to isolate the behavior but in vain!

Let's say a simple task of 40 hours starting on Monday the 10th supposed to finish on Friday the 14th. Then on the Wednesday I click 100% completed.

In my mind, I the actual finish date should switch from N/A to 12th but instead it shows the 14th, which is the original finish date. Makes no sense to me!

Any idea?

Last edited by patrickd123; 07-15-2014 at 08:53 AM.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Unexpected behavior of actual finish Changing Actual Finish dates changes original Finish dates SomewhereinTX Project 3 12-20-2013 10:25 AM
Unexpected behavior of actual finish duration vs actual start and finish dates ketanco Project 1 12-14-2011 09:06 AM
MS Project able to import actual start and or actual finish date from Excel? mhacker Project 0 04-26-2010 11:29 AM
Document Format: unexpected changes JMB^3 Word 1 08-19-2009 01:12 PM
Unexpected Server Response GreenAccord Project 0 01-31-2006 12:52 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 02:37 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft