JulieS JulieS is offline Duration days changing when updating % complete Windows 7 64bit Duration days changing when updating % complete Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Were you supposed to be more than 10% complete as of the status date? If you look at the Gantt chart - does the bar appear to be split - separated by dots?

If so, your option settings (Advanced) are likely moving the remaining parts of the work after the status date, creating the split in work. Do you have resources assigned to the tasks?

Also, it should not be necessary to press F9 to calculate the project. Ensure your calculate after each project (Options) is set to yes.
Reply With Quote
Reply



Similar Threads
Thread Thread Starter Forum Replies Last Post
Physical % Complete and Task Duration ChuckM Project 3 02-09-2014 09:21 AM
Change Resource Time vs. Duration when Updating Work column lylel Project 3 07-23-2012 06:09 PM
Duration days changing when updating % complete total slack not changing when changing duration ketanco Project 1 02-11-2012 07:23 AM
updating status date and actual duration ketanco Project 5 01-27-2012 07:32 AM
Duration days changing when updating % complete baseline duration of summary not updating. why ketanco Project 1 12-14-2011 09:07 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:37 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft