Q1. How to create a calendar with every other Saturday as working time?

A1. I can easily modify the standard / new generated calender, but we can only mark all Saturdays off. I want to mark 1st and 3rd Saturday off for 4 years calender, because if we modify the calendar manually, it takes alot of time.

Q2. How to copy that calendar to Global?
A2. Already known.

Q3. About version?
A3. Currently I am using MS project 2007, while I already searched the same in 2013 but same problem occurs.

Waiting for your reply.

Regards,

Arif
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Word 2013 macro to generate last day of each week (Saturday) CrabApple Word 1 11-08-2013 02:40 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:30 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft