milestone with more than 0 day duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default milestone with more than 0 day duration


in the milestone column i marked yes for an activity of 4 days duration (which happens to be a critical activity). and it became a milestone, still with 4 day duration but it is not shown as critical anymore , it is not in red at least. is it still critical? how does a milestone with a duration differ from a milestone of 0 duration? when we say milestone we understand by default 0 day correct?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
milestone with more than 0 day duration Is my Milestone working that way it's suppose to? Enuhseh207 Project 1 02-23-2014 09:24 AM
Milestone durations fraserm Project 4 01-13-2012 08:43 AM
milestone with more than 0 day duration calculating duration ketanco Project 5 12-15-2011 07:15 PM
milestone with more than 0 day duration Duration does not change caz46 Project 1 05-17-2011 07:51 AM
Project 2010 - Milestone Font Colour OTPM Project 1 05-11-2011 03:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 06:53 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft