milestone with more than 0 day duration
in the milestone column i marked yes for an activity of 4 days duration (which happens to be a critical activity). and it became a milestone, still with 4 day duration but it is not shown as critical anymore , it is not in red at least. is it still critical? how does a milestone with a duration differ from a milestone of 0 duration? when we say milestone we understand by default 0 day correct? |
|
Similar Threads | ||||
Thread | Thread Starter | Forum | Replies | Last Post |
Is my Milestone working that way it's suppose to? | Enuhseh207 | Project | 1 | 02-23-2014 09:24 AM |
Milestone durations | fraserm | Project | 4 | 01-13-2012 08:43 AM |
calculating duration | ketanco | Project | 5 | 12-15-2011 07:15 PM |
Duration does not change | caz46 | Project | 1 | 05-17-2011 07:51 AM |