You may mark any non zero duration task as a milestone through Task Information, Advanced. I never do it as I follow the usual definition of milestones = zero duration.
The color of the task bar does not necessarily indicate that the task is not critical. Check the Total Slack for the task to see if it is critical. |
|
![]() |
||||