#3
|
|||
|
|||
![]()
well the program marked it as a milestone and that is my question. how can a 4 day activity be a milestone? in addition to marking it as a milestone, the program also made it noncritical (as least it is not red in color anymore). so my question still stands... anyone?
|
|
![]() |
||||
Thread | Thread Starter | Forum | Replies | Last Post |
![]() |
Enuhseh207 | Project | 1 | 02-23-2014 09:24 AM |
Milestone durations | fraserm | Project | 4 | 01-13-2012 08:43 AM |
![]() |
ketanco | Project | 5 | 12-15-2011 07:15 PM |
![]() |
caz46 | Project | 1 | 05-17-2011 07:51 AM |
Project 2010 - Milestone Font Colour | OTPM | Project | 1 | 05-11-2011 03:22 AM |