  #3  
Old 06-16-2014, 06:25 AM
ketanco ketanco is offline milestone with more than 0 day duration Windows 7 64bit milestone with more than 0 day duration Office 2010 64bit
Expert
milestone with more than 0 day duration
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

well the program marked it as a milestone and that is my question. how can a 4 day activity be a milestone? in addition to marking it as a milestone, the program also made it noncritical (as least it is not red in color anymore). so my question still stands... anyone?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
milestone with more than 0 day duration Is my Milestone working that way it's suppose to? Enuhseh207 Project 1 02-23-2014 09:24 AM
Milestone durations fraserm Project 4 01-13-2012 08:43 AM
milestone with more than 0 day duration calculating duration ketanco Project 5 12-15-2011 07:15 PM
milestone with more than 0 day duration Duration does not change caz46 Project 1 05-17-2011 07:51 AM
Project 2010 - Milestone Font Colour OTPM Project 1 05-11-2011 03:22 AM

Other Forums: Access Forums

All times are GMT -7. The time now is 12:24 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft