Hi,
I have a case where a task could be done by either of 3 person of my team of 12 persons I can't assign the 3 of them at 100% to the task because it would block 3 full time ressource for that period when only one is needed. I cannot assignt the 3 of them at 33% because it would turn out later that one is under assigned and 2 others are over assigned, once I assign the one person I choose. I think I saw somewhere that the server version allows to define generic resource that later turns into an actual resource being assigned. But I have the standalone version. Is there a way to mimic that feature in this version? Thanks! |
|
![]() |
||||