You can create "generic" resources (by title for example) and then replace that resource with a named resource at another time. You need to remember to do the replacement with the named resource.

Is there a reason why you are not just assigning the named resource and then reviewing availability as you get closer to the task? I would pick one of the three and assign them at 100%. As you get closer to the task date - replace that resource as needed.