Default Resource vs. Assignment

Hi Julie,

I cannot select Assignment as field type for task summary name, only resource. It is greyed out.
Any idea?
Any setup wrong?

Thanks
Bumpui

Quote:
Originally Posted by JulieS View Post
The screen shot from above I believe is exactly what you need to do.
  1. Apply the Resource Usage view.
  2. Click the View Ribbon.
  3. Click the Group drop down.
  4. Select New Group.
  5. Create the group as I have shown in the screen shot.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Usage View Inactive tasks and resource usage view codeghi Project 1 05-05-2014 06:59 AM
Resource Usage view does not correctly export to a Visual Report cergon Project 3 04-25-2014 06:10 AM
Resource Usage View project 2010 resource usage runejors Project 1 04-04-2013 05:55 AM
Resource Usage View MS Project - Resource usage printout scrinmemphis Project 1 02-22-2013 02:30 PM
Resource Usage sheet - options Andy Bain Project 1 11-05-2010 12:42 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:44 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft