Plan vs. Resource Pool
Hi JulieS
actually I found out how to do it in the Planning MS P.
I grouped it (still couldnt find the window you mentioned) and it displays exactly what I want.
Thanks
But:
We have MSPs for projects and projects run parallel.
so I can see what I need on a per project basis, but I would also like to see it for all projects on a resource basis. So I used my resourcepool, where I also have groups (teams again).
But here I can see the resource name, the work per resource name, the group he is in and the project.
But I do not get the summary tasks and strangely I do not get the sum of all working days for this group. I would have to export it and then add it up.
Any possibility to do this here?
Thanks
Bumpui
|