Default

True - you can't use fixed duration tasks as hammock tasks - as the duration is recalculated based upon the change in start and finish dates.
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Multiple resource Dependencies / Mapping Sherry Project 3 04-03-2014 08:03 AM
Cross Project Dependencies OTPM Project 6 01-18-2014 07:52 AM
single task with combine SS and FF dependencies Task not rolling up after single task was baselined Hwlr Project 1 06-05-2013 03:43 PM
Assigning a single task to a team or group djcozens Project 1 07-09-2012 05:44 AM
Filter indirect dependencies SirPercival Project 1 07-04-2012 01:03 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 10:18 PM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2025, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2025 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft