Inactive tasks and resource usage view
 
Join Date: Jan 2010
Posts: 38
codeghi is on a distinguished road
Default Inactive tasks and resource usage view

Hello, in Project 2010 I often use the inactive task feature that allows me to model changes faster without destroying the project schedule.
But there is a problem: when I apply the "Resource Usage view" and create a group that groups by name and then by project, MS Project continues to calculate the inactive tasks as work effective tasks.
How could I fix it?
Reply With Quote
 



Similar Threads
Thread Thread Starter Forum Replies Last Post
Resource Usage view does not correctly export to a Visual Report cergon Project 3 04-25-2014 06:10 AM
Inactive tasks and resource usage view Exporting Resource Usage data to Excel samg54 Project 1 08-02-2013 05:28 AM
Inactive tasks and resource usage view project 2010 resource usage runejors Project 1 04-04-2013 05:55 AM
Inactive tasks and resource usage view MS Project - Resource usage printout scrinmemphis Project 1 02-22-2013 02:30 PM
Resource Usage sheet - options Andy Bain Project 1 11-05-2010 12:42 PM

Other Forums: Access Forums

All times are GMT -7. The time now is 11:24 AM.


Powered by vBulletin® Version 3.8.11
Copyright ©2000 - 2024, vBulletin Solutions Inc.
Search Engine Optimisation provided by DragonByte SEO (Lite) - vBulletin Mods & Addons Copyright © 2024 DragonByte Technologies Ltd.
MSOfficeForums.com is not affiliated with Microsoft