Default Inactive tasks and resource usage view

Hello, in Project 2010 I often use the inactive task feature that allows me to model changes faster without destroying the project schedule.
But there is a problem: when I apply the "Resource Usage view" and create a group that groups by name and then by project, MS Project continues to calculate the inactive tasks as work effective tasks.
How could I fix it?