I have created a small schedule in Project 2007 that has 71 lines. I created it without assigning resources but I have used predecessors to define the critical path. Virtually every task shows critical even though several have weeks of float available. I have tried to simplify the predecessor links by making them all "Finish to Start" and the constraint types to "As soon as possible" but to no avail. Every task shows critical bar style in the Gantt chart. What am I doing wrong? |
| Thread Tools | |
| Display Modes | |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
filter 'Task name' shows all tasks
|
Intruder | Project | 5 | 02-02-2014 07:29 AM |
| Question about tasks on critical path in MS Project schedule (with a twist) | SomewhereinTX | Project | 7 | 01-06-2014 03:07 PM |
| Can you either (a) float a page of different orientation or (b) rotate table? | New Daddy | Word | 9 | 11-14-2013 01:55 PM |
Sr. Citizen Question, Please: WORD Shows Blank, But Notepad Shows "Gibberish" ?
|
Robert11 | Word | 3 | 08-12-2013 12:35 PM |
analysing contractor schedule for critical path
|
ketanco | Project | 1 | 02-07-2013 06:49 AM |