Julie:
That did it! Thanks so much. I have always used Constraint Type: Must Finish On for my "Project Complete" or "Specified Completion" task. I inadvertently clicked the down arrow next to the Deadline: text box and it inserted todays date by default. I didn't even notice it. Problem solved. After 14 years I'm still learning this software ;P