![]() |
|
|||||||
|
|
Thread Tools | Display Modes |
|
#3
|
|||
|
|||
|
Julie:
I added "Total Slack" field (new field to me) but all the calculated values are large negative numbers (???). The duration of my project is May 5 thru September 12, 2014, a total of 127 calendar days and the float calculates as -288 days! Can I p.m. a copy of my schedule to you? |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
filter 'Task name' shows all tasks
|
Intruder | Project | 5 | 02-02-2014 07:29 AM |
| Question about tasks on critical path in MS Project schedule (with a twist) | SomewhereinTX | Project | 7 | 01-06-2014 03:07 PM |
| Can you either (a) float a page of different orientation or (b) rotate table? | New Daddy | Word | 9 | 11-14-2013 01:55 PM |
Sr. Citizen Question, Please: WORD Shows Blank, But Notepad Shows "Gibberish" ?
|
Robert11 | Word | 3 | 08-12-2013 12:35 PM |
analysing contractor schedule for critical path
|
ketanco | Project | 1 | 02-07-2013 06:49 AM |